45 80 pound bags will result in 1 yard of concrete
There are approximately 27 cubic feet in a cubic yard, and an 80-pound bag of concrete typically yields about 0.6 cubic feet. Therefore, to fill one cubic yard, you would need about 45 bags of 80-pound concrete.
According to the related link below; the required amount to cover 1 square yard with 4 inches of concrete is 6.6 60 pounds bags.
Each 60 pounds bag of ready mix concrete will make .45 cubic foot of concrete. There are 27 cubic feet in a cubic yard. You will need 60 bags of 60 pound premixed concrete to make 1 cubic yard.
One cubic yard of concrete typically weighs about 4,000 pounds. Since each 80-pound bag of concrete contains approximately 0.6 cubic feet, you would need about 45 bags to equal one cubic yard of concrete. Specifically, 1 cubic yard equals 27 cubic feet, so dividing 27 by 0.6 gives you around 45 bags.
A typical 80-pound bag of concrete mix yields about 0.6 cubic feet of concrete. A 3-yard mixer has a capacity of 81 cubic feet (3 cubic yards). To fill the mixer, you would need approximately 135 bags of 80-pound concrete mix, since 81 cubic feet divided by 0.6 cubic feet per bag equals about 135 bags.
20
Forty five 80 pound bags of cement are needed to make one cubic yard of concrete.
According to the FAQ on the Sakrete web site, Sixty of their sixty pound bags of High Strength concrete mix will be required to make a cubic yard of concrete.
about 60 60lb bags
According to the related link below; the required amount to cover 1 square yard with 4 inches of concrete is 6.6 60 pounds bags.
Depending on the use of the concrete, between 5-6 bags.
Each 60 pounds bag of ready mix concrete will make .45 cubic foot of concrete. There are 27 cubic feet in a cubic yard. You will need 60 bags of 60 pound premixed concrete to make 1 cubic yard.
27 bags of 30kg bags of concrete bargs
bags of what?
about 60 60lb bags
it takes 45 Bags of 80# mix to make a cubic yard
A typical 80-pound bag of concrete mix yields about 0.6 cubic feet of concrete. A 3-yard mixer has a capacity of 81 cubic feet (3 cubic yards). To fill the mixer, you would need approximately 135 bags of 80-pound concrete mix, since 81 cubic feet divided by 0.6 cubic feet per bag equals about 135 bags.