First convert the thickness, 4 inches to feet so we are using the same units for sq ft and thickness. That is 4 inches is 4/12 ft or 1/3 ft Then multiply the sq ft by the thickness to get the cubic measure. That is 400 sq ft by 1/3 ft = 133.33 cu ft. Convert that to cubic yards. Since there is 3 ft to a yard, there are 3 x 3 x 3 = 27 cu ft in a cubic yard. So divide the cu ft by 27 to arrive at cu.yds. That is 133.33/27 = 4.94 cu yards say 5 cubic yards. If the result is required in cubic meters then multiply by 0.765. That is 4.94 x 0.765 = 3.78 cubic meters
2.15
14.81 yds
you can do the math: LXWXD DIVIDED BY 27
625 times 0.5 = 312.5 cubic feet will be needed
how many cubic feet in a yard of concret
2.15
14.81 yds
you can do the math: LXWXD DIVIDED BY 27
625 times 0.5 = 312.5 cubic feet will be needed
how many cubic feet in a yard of concret
A 9x9 foot slab 4 inches thick requires a minimum of 1 cubic yard. If you go to 6 inches thick you will need 1.5 cubic yards.
A 10-foot round slab at 4 inches requires 1 cubic yard.
55
Volume of concrete needed = 4 x 12 x 1/3 = 4 x 4 = 16 cubic feet
4300 x .66 * = 2838 cubic feet / 27 = 105.11 cubic yards. ( *.66 = 8" )
Allow 5.5 to 6 yards. Always allow for wastage, underrunning forms, etc.
If it is 4 inches deep/thick, 2 cubic yards. If it is 6 inches deep/thick, 3 cubic yards.