A 52' x 48' by 4" pad requires 30.8 cubic yards. If you go up to 6" thick you would need 46.2 cubic yards.
16 yards
17.3 cubic yards will do it.
105 m = 114.829 yrd
It starts curing the second they put water in it.
A 20'x35'x4" drive requires 8.64 cubic yards.
16 yards
There are 16 yards in 48 feet
The term "yards" of concrete means cubic yards.
You will need 0.56 cubic yards of concrete.
You will need 17.8 cubic yards of concrete.
1.67 cubic yards.
37.03 yards
1.8 cubic yards will do it.
0.89 cubic yards.
You can't express a volume of concrete in yards.
532.4074 yards of concrete, round up to 533 yards.
.029 cubic yards of concrete weighs aproximately 93.96lbs